NOUS /Anglais SPA /Espagnol VIE /vietnamien IDENTIFIANT /indonésien URD /ourdou ÈME /thaïlandais POUR /swahili CE /Haoussa DEPUIS /Français RU /russe NOUS ACHETONS /arabe
Guide complet pour le calcul de la puissance totale et la sélection du transformateur pour la centrale à béton HZS50
25 septembre 2025

 I. Detailed Analysis of HZS50 Mixing Plant Power Components

 As a representative model of medium-sized concrete mixing plants, the power supply configuration of the Centrale à béton HZS50directl affects production efficiency and operational stability. Let's understand it requirements through a detailed power supply analysis.

 

HZS50 concrete batching plant-2.jpg

Power Supply Configuration Table for Major Equipment

Device Name

power(kW)

Working characteristics

JS1000mixer

218.5

High starting current

Aggregate elevator

15

Intermittent operation

Convoyeur à vis

211

Intermittent operation

PLD1600Batching machine

34

Intermittent operation

air compressor

4

Intermittent operation

Water pump (water supply)

2.2

Intermittent operation

Water pump (drainage)

1.1

Intermittent operation

Admixture pump

0.55

Intermittent operation

Dust removal system

22.2

Intermittent operation

Puissance totale

98.25

Intermittent operation

 

II. Professional Transformer Selection Recommendations

Detailed Total Power Calculation:

Total Power of Basic Equipment: 98.25kW

Auxiliary System Power:

- Lighting System: 5kW (Onsite Lighting + Control Room)

- Control System: 3kW (PLC + Computer + Monitoring)

- Household Power: 8kW (Office + Dormitory)

Total Auxiliary Equipment Power: 16kW

Calculation Parameters:

- Simultaneous Utilization: 0.82 (based on equipment operating characteristics)

- Power Factor: 0.85

- Actual Required Power: (98.25 + 16) × 0.82 = 93.7kW

- Minimum Transformer Capacity: 93.7 / 0.85 = 110.2kVA

 Recommended Transformer Specifications:

1. Economic Configuration: 125kVA

- Applicable Scenario: Single-Shift Production (8-Hour Operation)

- Load Factor: 87.4%

- Advantages: Low investment cost and meets basic requirements

2. Standard Configuration: 160kVA ⭐⭐⭐⭐⭐

- Applicable Scenario: Two-Shift Production (16-Hour Operation)

- Load Factor: 68.3%

- Advantages: Stable operation, 30% expansion capacity reserved

- Disadvantages: High initial investment

3. High-Performance Configuration: 200kVA

- Applicable Scenario: Three-Shift Continuous Production

- Load Factor: 54.6%

- Advantages: High operational flexibility, supports future expansion

- Disadvantages: Highest investment cost

 III. Power System Optimization Solution

Energy Saving Measures:

1. Motor System Optimization

- Select IE3 high-efficiency energy-saving motors

- Implement power factor correction

2. Operation Management Optimization

- Develop a scientific production scheduling plan

- Establish an équipement idle monitoring system

- Implement peak and off-peak electricity pricing strategies

3. Maintenance Optimization

- Regularly check motor operating conditions

- Maintain proper lubrication of the transmission system

- Promptly replace aging electrical components

 Safety Protection Configuration:

1. Overload Protection System

- Intelligent circuit breaker protection

- Thermal relay protection

- Motor Overload Protector

2. Lightning Protection System

- Secondary Lightning Protection

- Protector

- Reliable Grounding System

3. Emergency Protection System

- Emergency Shutdown Device

- Leakage Protection System

- Phase Loss Protection


HZS50 concrete batching plant-1.jpg


 IV. Expansion Configuration Plan

Power Requirements for Equipment Expansion

Extension Project

Add a device

Increase power(kW)

Transformer Addition

Add 1 cement silo

Screw conveyor + dust collector

13.2

+15kVA

Adding a refrigeration system

Chiller + water pump

18.5

+20kVA

Add a heating system

Hot water boiler + circulation pump

22.0

+25kVA

 

V. FAQs

Q1: How should I choose a transformer for different production modes?

A: Choose based on production intensity:

- Single-shift production: 125kVA

- Double-shift production: 160kVA

- Continuous production: 200kVA

Q2: What are the effects of grid voltage fluctuations?

A: When the voltage fluctuates by ±10%:

- A 125kVA transformer may be overloaded

- A 160kVA transformer can still operate stably

- It is recommended to install a voltage stabilizer

Q3: How is electricity bill calculated?

 A: Taking a 160kVA transformer as an example:

- Monthly electricity consumption: approximately 25,000 kWh

- Electricity bill: approximately$2857/month

- Transformer losses: approximately $114/month

 VI. Professional Advice and Service

We recommend considering the following factors when selecting a transformer:

1. Power requirements of existing equipment

2. Future expansion plans

3. Local power grid quality

4. Production schedule

5. Investment budget constraints

 Our professional technical team can provide:

- Free site surveys

- Customized solution design

- Equipment selection recommendations

- Installation and commissioning guidance

- After-sales maintenance services

If you need a more detailedcentrale à béton power calculation or customized solution, please provide your specific requirements. Machines Tongxinwill provide professional technical support and services.

Contact us: Provide site dimensions and production requirements so we can customize a power solution for you!